Heron's Park - land at Dappers Lane

Development is underway on this site and will provide 84 dwellings out of which 25 units will be affordable, this is being constructed by Charles Church developers.

The Strategic Allocation will provide contributions towards education facilities and a new Secondary School in the District, A259 Highway improvements and contributions towards Flood Alleviation and Sports Facilities in Palmer Road.

The full planning application has been approved under planning application A/76/20/PL

Latest news:

November 2023: 

  • the local play area has been opened

March 2023:

  • the drainage scheme verification condition has been submitted and is currently being reviewed by our drainage engineers

February 2023:

  • first occupations have taken place on-site

Arboricultural Method Statement and Tree Protection Plan

An Arboricultural Method Statement (AMS) outlines the working methods for construction workers to follow and adhere to during development. The Tree Protection Plan (TPP) forms part of the Arboricultural Method Statement and details the location of protection measures, such as the position of tree protection fencing. The following plans have been submitted:

  • Arboricultural opportunities and constraints assessment- July 2018 was approved under the planning application

Construction Management Plan

A construction management plan is a document that includes detailed information designed to minimise potential construction impacts on the environment taking into account logistics, traffic management and other impacts. The following plans have been submitted:

Useful information

Permitted hours

No construction/demolition activities shall take place other than between:

  • 8am and 6pm on Mondays to Fridays inclusive
  • 8am and 1pm on Saturdays
  • not at any time on Sundays or Public Holidays

 Permitted Development Restrictions

Permitted development rights are provided by the Town and Country Planning (General Permitted Development) Order 1995 (the GPDO). This allows certain types of development to proceed without the need for planning permission. However local planning authorities are allowed to remove permitted development rights in some or all of its area by issuing an Article 4 Direction; or remove those rights on the original, or any subsequent, planning permission for the house. Where permitted development rights have been removed in either of these ways, a planning application will be needed for development. The following conditions have been imposed:

  • Condition 25: “Notwithstanding the provisions of Class A, A.1, (g) within Part 1 of Schedule 2 of the Town and Country Planning (General Permitted Development) (England) Order, 2015 (or any Order revoking or re-enacting this Order) no rear extensions to the dwelling houses shall be erected within the curtilage of the dwellings hereby permitted unless planning permission is first granted by the Local Planning Authority on an application in that behalf

Archive news

Previous planning application news for this site is as follows:

August 2021:

  • construction works will be taking place between 6 September 2021 and 1 October 2021 to form the Bellmouth (entrance to the site) as per the Section 278 agreement relating to highway works

August 2021:

  • further preparatory works will be undertaken on the site during the week commencing 9 August 2021 this will include borehole ground investigations

June 2021:

  • preparatory works relating to planning permission, will be undertaken on 28 June 2021, relating to the formation of a site entrance, formation of a parking area, erection of site boundary fencing and other preparatory works which may include some heavy plant equipment moving onto the site

May 2021: 

  • some site clearance works are taking place at the entrance to the site to enable an archaeological team to gain access

May 2020: 

  • application A/76/20/PL submitted for land West of Dappers Lane  

April 2020: 

  • land West of Dapper Lane, a draft plan has been produced by Persimmon Homes for 84 houses.  Please Note; When a formal planning application is submitted there will be an opportunity for comments to be made regarding the application

Masterplan

Heron's Park site layout (land at Dappers Lane - Angmering)

Please click on the image below to enlarge.

Heron's Park map

 

 

 

 

 

 

 

 

Alternative text - a map of Heron’s Park development site. This shows the proposed layout of houses and open spaces. The majority of open space is on the southern edge of the map.
Wording on map includes the below:

Developer: Persimmon (together we make a home) Persimmon Homes Thames Valley, Persimmon House, Knoll Road, Camberley, Surrey, GU15 3TQ (tel: 01276 808080)

Site: Dapper's Lane, Angmering Littlehampton

Drawing title: Coloured Planning Layout - 84 units

Date: November 2019

Scale: 1:500@A1

Drawing ref: A77-PL-02

Drawing status: preliminary

Please note the masterplan above is for illustrative purposes only and details are subject to change.

IFS

The Infrastructure Funding Statement (IFS) provides an update on all matters regarding developer contributions Section 106 (S.106) and Community Infrastructure Levy (CIL) during the previous financial year.

Our first IFS was published in September 2020 to cover the period from April 2019 to 31 March 2020. Please see our current IFS statement.

We collect all CIL contributions for all types of Infrastructure (from 1 April 2020) but we do not collect S.106 contributions for the provision of schools, highways, libraries or the fire service (although, in some cases, S.106 for these items are retained for these projects, in agreement with the county council). In most cases, these items are the responsibility of West Sussex County Council (WSCC). Therefore our IFS should be read in conjunction with the WSCC IFS to identify how S.106 from specific development sites has been spent across the board.   

If you wish to contact us regarding any of the strategic sites, please