16 October 2023
All works are now complete. Some minor remedial work will be completed in the coming weeks. The Road Safety Audit has been completed and WSCC are due to sign off imminently. This completes the project and no further updates will be provided under this section.
18 August 2023
All paving works are now complete in Phase 1. The final resurfacing works will be completed over 2 weekends, finishing 24 September 2023. Phase 2 and 3 are fully complete, with some cleaning and re-sealing work planned over the coming months.
20 July 2023
Phases 2 and 3 are fully complete and Terminus Road works will be completed by 6 August, with the exception of the resurfacing works, which will require a full road closure for 2 weekends (16/17 September and 23/24 September).
22 May 2023
The Clock Tower lighting is being installed imminently, new tree pots will be installed in June. Terminus Road works are progressing to programme and works around the station are due to commence in June.
24 April 2023
Works to the High Street and surrounding area are now complete. An additional 22 cycle stands, an extra bench, additional signage, and lighting to the clock tower are now all installed, the tree pots for Beach Road and one on the High Street will be installed in June.
Phase 1 works (Terminus Road) continue to schedule. These works will be completed in September 2023.
21 March 2023
Works to the High Street and surrounding area are now complete. Additional funding from UK Prosperity Fund has enabled us to deliver a further 22 cycle stands, an extra bench, additional signage, tree pots for Beach Road and one on the High Street to replace trees that could not be planted due to underground services and lighting to the clock tower. All these works will be undertaken over the coming months, but are not expected to cause any disruption to pedestrians or traffic.
Phase 1 works (Terminus Road) continue to schedule. These works will be completed in September 2023.
21 February 2023
Beach Road, East Street, Clifton Road, Duke Street and High Street works are now complete, although some remedial works and cleaning are happening. No further disruption is planned as a result of the work. Parking enforcement will start again on 27 February across all areas listed.
23 January 2023
High Street, Clifton Road, Beach Road, Duke Street work areas have been re-opened post-Christmas, with paving works continuing to completion on Beach Road. Outstanding tree planting on Beach Rd is programmed for February 2023. Remedial works are being undertaken where required. All other areas are complete, with the exception of Duke Street, which will be resurfaced in early February. Additional signage and other minor improvements will take place over the coming weeks.
Terminus Road: Traffic management, including temporary lights, have been re-installed post-Christmas break and works are continuing to the southern footway between the junction of Terminus Place and Arundel Road. These works include drainage, kerb re-alignment and new paving.
19 December 2022
Paving works are complete on the High Street, Clifton Road, Duke Street and St Martins Lane. Paving works are continuing on Beach Road. Carriageway surfacing is complete to Clifton Road, Surrey Street/High Street and East Street/High Street. Remaining tree planting on Beach Road is programmed for February 2023. The Christmas Lighting Event took place on Saturday, 19 November.
Terminus Road Works: Works commenced on Monday 14 November 2022, beginning on the southern footway at the junction of Terminus Road/Terminus Place working eastwards. These works include drainage, kerb re-alignment and new paving.
18 November 2022
The High Street is now fully reopen and the Christmas Tree has been installed ready for the Christmas light switch on. Resurfacing work is ongoing in various locations and will complete in early December, except Beach Road which will be resurfaced in March 2023. Terminus Road improvements have commenced and are due to be completed in late summer 2023.
20 September 2022
Beach road will be re-open from Saturday 24 September 2022. The drainage works required have now been completed and the road has been made good, enabling us to reopen the road. There will be an additional closure in November to facilitate the resurfacing works and we will continue to work with businesses and residents to minimise the impacts.
18 August 2022
A temporary road closure on Beach Road will come into effect on 12 September for up to 3 weeks. There will be diversions in place and marshals at key locations to assist with managing traffic. This closure is necessary to enable gullies and drains to be connected to the main sewer located below and in the middle of Beach Road.
22 July 2022
A temporary road closure on Arcade Road will be enforced from 8 August 2022 so ducting can be laid across the road.
The results of our consultation for the introduction of loading time restrictions on High Street are in. Read our press release on the results for more information.
17 June 2022
The works programme for Beach Road has been changed to reduce the road closure duration down to approximately three weeks. This is to lessen the impact on traders. The closure is scheduled for Monday 12 September 2022 but is subject to change.
27 May 2022
A temporary road closure on Beach Road will be enforced from mid-September to carry out essential drainage works.
20 May 2022
NHS are currently dismantling the COVID-19 Test Centre in St Martins car park. It will be reopened for parking thereafter
31 March 2022
NHS will be removing the COVID-19 Test Centre in St Martins car park on 18 April 2022
18 March 2022
Funding has been secured for the delivery of Phase 1.
1 February 2022
New information available, please see addressing your concerns.
21 January 2022
A small temporary road closure to the section of High Street between the entrance to Manor House car park and Lloyds Bank will take effect from Monday 24 January 2022 for approximately 4 weeks. Manor House car park will remain open with access being unaffected.
10 January 2022
The project was launched with a breaking ground event (please click image to view in full size)
21 December 2021
- Part of St Martins car park will be closed from 3 January 2022
- The location of Littlehampton’s Friday market may change throughout the project
- Our contractors will be on-site between 7:30am to 5:30pm Monday to Friday (daylight hours dependent)
16 December 2021
- Our contractors have released details of their construction timetable. This is now available to view, download or print:
- Artist's images of Phase 1 (Terminus Road) are also now available.