Littlehampton Seafront Scheme update - 29 November 2024
This week, the sight of an unusual piece of machinery drew small crowds of people to watch concrete being poured for the base of the new foreshore building. With this in place, the contractor will be starting to build the walls of the building.
The toilet block has seen great progress with multiple drainage pipes installed and is ready for the concrete base to be laid.
Other activities which will be taking place include preparation work to the car park, further drainage across the site and pipework for the water play feature. The car park phasing is being reviewed with the contractors and an update will be given on this soon. It is expected the main area of West Green car park will remain open until early January.