Littlehampton seafront scheme update – 28 March 2025

Text Littlehampton seafront | Construction phase plans. Phase 3 Spring 2025 to summer 2025. - contractors compound remains on Banjo Road - work to Banjo Road - work to West green car park - utility service work. The image is a construction map - with sectioned areas and a yellow circle (Phase 3 work area) a blue circle (Contractors compound) and a red circle (Temporary toilets) text on map 'Pedestrian route between South Terrace and seafront - dotted line running along left side with ENTRANCE AND EXIT shown.The tarmac area of West Green car park has reopened following resurfacing this week and is ready to welcome visitors ahead of the Easter holidays.  

The updated plan shows the area available for parking.  

Neilcott Construction is continuing their work to improve the overflow area of the car park.