Littlehampton seafront scheme update – 24 February 2025
The contractors have now started work on improvements to the overflow car park. When the ground has been dug out to the correct levels, a new surface will be laid which allows the grass to grow through it.
Wall construction is also underway at the foreshore building and the beginnings of a roof can be seen on the toilet block.
Concrete has been laid in the water feature pools by a specialist sub-contractor and electrical connections are being made in the plant room.
At the south of the site earth banks have been formed.