Littlehampton Seafront Scheme update 10 January 2025
Work is back in full swing after the Christmas break with the installation of site storm drains and water supply for the new facilities. Neilcott Construction will also complete laying around 1,500 meters of underground pipework, needed to carry all the electrical cables across the site. Next week we expect brick laying to begin at the toilet block and foreshore building and scaffolding will be put up.
Temporary repairs have been made to the overflow area of West Green car park to enable the tarmac area to be closed off for improvements. The overflow area is being kept available for public use until the tarmac area is complete. If the condition of the overflow car park becomes unsafe due to poor weather, it may need to close for a period.
People walking along the promenade will be able to check out our new notice board which displays design information, a plan of the car park phasing and latest news updates.