Demolitions
You must notify us of all demolition works served under Section 81of the Building Act 1984. We require at least 6 weeks’ notice, so that we have time to notify all the statutory undertakers of the works, any adjoining owners/occupiers and other additional parties which could be affected by the works.
There are several statutory undertakers that must be notified. For further information and a list of these statutory undertakers, please contact us.